Base, Jacks & Stabilizers - Back

With four high capacity jacks and 2 stabilizer arms with jacks, you can feel safe working from any height.
Leveling
The stabilizer arm jacks are designed to stabilize the bases and are NOT INTENDED to carry excessive weight loads.
1. To level the front of the plaform from end to end, place a level on the FRONT traverse tube and use the FRONT jacks to make adjustments. Adjust the FRONT jacks until the unit is level.

2. To level the rear of the plaform from end to end, place a level on the front of the BASE TOWER and use the REAR jacks to make adjustments. Adjust the REAR jacks until the unit is level.

3. To plumb the towers from front to rear, place a level on the side of the BASE TOWER and use the STABILIZER jacks to make adjustments. Adjust the STABILIZER jacks until the tower is vertically level.

NOTE: This may reposition the REAR traverse tube slightly out of level. |